New house construction
Job address - 300 Sequoia Avenue, Palo alto, CA 94306-1045
Basement - 1,259 sq. ft
1st floor - 1,213.5 sq. ft
2nd - floor - 999 sq. ft
1 car detached garage (not shown) - 184.3 sq. ft

 

 

 

 

 

 

 

 

 

 

 

 

 

Old "charming house" was bought
 March 10, 2000
Surveyor Map: topo and boundary - done
 April 18, 2000
Soil Investigation service. Soil Report done
 December 31, 2000
Architect starts
 April 08, 2004
Bother. Engineer Preparation Stage
 August 01, 2004
Building Permit ready. Taxes, fees, etc. paid
 September 22, 2004
We start. Demolition
 September 27, 2004
Surveying and Holes drilling for Stitch peers
 September 29, 2004
Basement. Digging the trench for basement
 October 04, 2004
Basement. Forms installation start
 October 07, 2004
Basement. Gravel and plumbing done
 October 13, 2004
Basement. Floor waterproofing done
 October 18, 2004
Basement. Floor armature done
 October 25, 2004
Basement. Cement was poured, concrete floor done
 October 28, 2004
Basement. Walls Deck (decking)
 November 05, 2004
Basement Walls Deck (armature istallation)
 November 14, 2004
Basement Walls ready to be poured
 November 19, 2004
Basement Walls poured and ready
 November 27, 2004
Basement framing 90% is done
 December 19, 2004
1st floor framing 80% is done
 December 25, 2004
2nd floor framing 75% is done
 December 31, 2004
2nd floor framing 85% is done
January 07, 2005
Framing done, Roof covered by felt February 05, 2005
Sheetrock delivered, etc February 20, 2005
Roof tile delivered, etc
March 12, 2005
Ready for both stucco and sheet rocking March 18, 2005
Insulation done March 26, 2005
Stucco. 2nd (Brown) coat 65 % done April 25, 2005
House in progress
June 23, 2005
House inside
August 24, 2005
Landscape, driveway and facades are finished September 10, 2005
   
Flyer
 
   
   
   
   
   
   
   
Plumbing
 
HVAC - Heat, Ventilation, Air Conditioning
 
Windows installed
 
Framing in progress
 
Roofing felt done
 
Interior Doors Installed
 
Plumbing done
 
Electrical done
 
SheetRock
 
Hardwood floor Brazilian Cherry
May 10, 2005
Kitchen installed
May 10, 2005
Painting done
April 26,2005
Marble Tile in 4 Bathrooms
May 30, 2005
Stucco done Roof finish
May 20, 2005
Landscaping done
May 31, 2005
 
 
Garage door installation
 
Fire-place
 
Dale Walter
 
Air conditioner with Puron Refrigerant
 
Grasscrete plastic
 
Basement floor
 
Grass paving overview
 
Grasscrete
 
Grass driveway and landscaping
 
Doors
 
Sauna
 
Low-voltage Network
 
Stair beeam
 
Fence
 
Roofing
 
Santa Clara Lumber & Millwork
 
Bay Area Lumber Inc
 
Bruce Bauer Lumber & Supply
 
Southern Lumber Co
 
Minton's Lumber & Supply Co
 
Sunnyvale Lumber Inc
 
Stainless sink installation
Granite Notch and U-channel
 
Framing Material Takeoff
 
Living Room with Fireplace
 
 
 
The SWG Power Venter
 
The SWG Power Venter Control Kit
 
Through-The-Wall TTW2 Gas Water Heater
 
75 Gallon American PROLine™ Power Vent Powerflex™ Residential Gas
 
Instant Hot Water system
 
Plumber Claim
 
Roofer claim
 
Purgatory