| |
New house
construction
Job address -
300 Sequoia Avenue, Palo alto, CA 94306-1045
Basement - 1,259
sq. ft
1st floor -
1,213.5 sq. ft
2nd
- floor - 999
sq. ft
1 car detached
garage (not shown) - 184.3 sq. ft
Old "charming
house" was bought
|
March 10, 2000
|
Surveyor Map: topo and boundary - done
|
April 18, 2000
|
Soil
Investigation service. Soil Report done
|
December 31, 2000
|
Architect starts
|
April 08, 2004
|
Bother. Engineer
Preparation Stage
|
August 01,
2004
|
Building Permit
ready. Taxes, fees, etc. paid
|
September
22, 2004
|
We start.
Demolition
|
September 27, 2004
|
Surveying and
Holes drilling for Stitch peers
|
September
29, 2004
|
Basement.
Digging the trench for
basement
|
October 04, 2004
|
Basement. Forms
installation start
|
October 07, 2004
|
Basement. Gravel and plumbing done
|
October 13, 2004
|
Basement. Floor
waterproofing done
|
October 18, 2004
|
Basement. Floor armature
done
|
October 25,
2004
|
Basement.
Cement was poured,
concrete floor done
|
October 28, 2004
|
Basement.
Walls Deck (decking)
|
November
05, 2004
|
Basement
Walls Deck (armature
istallation)
|
November
14, 2004
|
Basement
Walls ready to be poured
|
November
19, 2004
|
Basement
Walls poured and ready
|
November
27, 2004
|
Basement
framing 90% is done
|
December
19, 2004
|
1st floor
framing 80% is done
|
December
25, 2004
|
2nd floor
framing 75% is done
|
December
31, 2004
|
2nd floor
framing 85% is done
|
January
07, 2005
|
Framing done,
Roof covered by
felt |
February 05, 2005 |
Sheetrock delivered, etc |
February 20, 2005 |
Roof tile delivered, etc
|
March 12, 2005 |
Ready for both stucco and
sheet rocking |
March 18, 2005 |
Insulation done |
March 26, 2005 |
Stucco. 2nd (Brown) coat 65 % done |
April 25, 2005 |
House in progress
|
June 23, 2005
|
House inside
|
August 24, 2005
|
Landscape, driveway and
facades are finished |
September 10, 2005 |
|
|
Flyer
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Plumbing
|
|
HVAC - Heat,
Ventilation, Air Conditioning
|
|
Windows
installed
|
|
Framing in
progress
|
|
Roofing felt done
|
|
Interior
Doors Installed
|
|
Plumbing done
|
|
Electrical done
|
|
SheetRock
|
|
Hardwood floor
Brazilian Cherry
|
May 10, 2005 |
Kitchen
installed
|
May 10, 2005 |
Painting done
|
April 26,2005 |
Marble Tile in 4
Bathrooms
|
May 30, 2005 |
Stucco done
Roof
finish
|
May 20, 2005 |
Landscaping done
|
May
31, 2005
|
|
|
Garage door
installation
|
|
Fire-place
|
|
Dale Walter
|
|
Air conditioner with Puron Refrigerant
|
|
Grasscrete plastic
|
|
Basement floor
|
|
Grass paving overview
|
|
Grasscrete
|
|
Grass driveway and landscaping
|
|
Doors
|
|
Sauna
|
|
Low-voltage Network
|
|
Stair beeam
|
|
Fence
|
|
Roofing
|
|
Santa Clara Lumber & Millwork
|
|
Bay Area Lumber Inc
|
|
Bruce Bauer Lumber & Supply
|
|
Southern Lumber Co
|
|
Minton's Lumber & Supply Co
|
|
Sunnyvale Lumber Inc
|
|
Stainless
sink installation
Granite Notch and U-channel
|
|
Framing Material
Takeoff
|
|
Living
Room with Fireplace
|
|
|
|
The SWG Power Venter
|
|
The SWG Power Venter Control Kit
|
|
Through-The-Wall TTW2 Gas Water Heater
|
|
75 Gallon American PROLine™ Power Vent Powerflex™ Residential Gas
|
|
Instant Hot Water system
|
|
Plumber Claim
|
|
Roofer claim
|
|
Purgatory
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|