February 20, 2005
Electric done 80%
Plumbing
done 85%
Heat and sheet
metal done 75%
Framing done 95%
Concrete - 95%
Sheetrock
delivered - 100%
Roof done felted
100%, roof tile 0%
Fence done 85%
|