March 12, 2005
House is loaded with both sheetrock and roof tile...
Pluming is done 85%
Heat ducking and sheet metal works are done - 95%
Electric wire is done - 95%
Master bath-room shower "hop mop" is done - 100%
Papering, i.e. "chicken wire" will be done in 3 days
Next step - inspection
After that - insulation and sheet rocking

Spring!

Rear elevation (facade) with sunken patio and stairway to the basement

Both front and rear porches are waterproofed by cupper

Roof tile are loaded