  New house 
  construction
  Job address -
  
  
  300 Sequoia Avenue, Palo alto, CA 94306-1045
  Basement - 1,259 
  sq. ft
  1st floor - 
  1,213.5 sq. ft
  2nd 
  - floor - 999 
  sq. ft
  1 car detached 
  garage (not shown) - 184.3 sq. ft
 
  
    
  
  
  
  
  
  
  
  
  
  
  
  
  
  
    | 
  Old "charming 
  house" was bought
     | 
    
  
   March 10, 2000
     | 
   
  
    | 
  
  Surveyor Map: topo and boundary - done
     | 
    
  
   April 18, 2000
     | 
   
  
    | 
  Soil 
  Investigation service. Soil Report done
     | 
    
  
   December 31, 2000
     | 
   
  
    | 
  
  
  Architect starts
     | 
    
  
   April 08, 2004
     | 
   
  
    | 
  
  Bother. Engineer 
  Preparation Stage 
     | 
    
   August 01, 
  2004
     | 
   
  
    | 
  Building Permit 
  ready. Taxes, fees, etc. paid 
     | 
    
   September 
  22, 2004
     | 
   
  
    | 
   
  We start. 
  
  Demolition 
     | 
    
   
   September 27, 2004
     | 
   
  
    | 
  Surveying and 
  Holes drilling for Stitch peers 
     | 
    
   September 
  29, 2004
     | 
   
  
    | 
   
  Basement. 
  Digging the trench for 
  basement 
     | 
    
   
   October 04, 2004
     | 
   
  
    | 
   
  Basement. Forms 
  installation start  
     | 
    
   
   October 07, 2004
     | 
   
  
    | 
   
  Basement. Gravel and plumbing done
   
     | 
    
   
   October 13, 2004
     | 
   
  
    | 
  
  Basement. Floor 
  waterproofing done  
     | 
    
  
   October 18, 2004
     | 
   
  
    | 
  
  Basement. Floor armature 
  done  
     | 
    
   October 25, 
  2004
     | 
   
  
    | 
  Basement.
  Cement was poured, 
  concrete floor done 
     | 
    
   October 29, 2004
     | 
   
  
    | 
  Basement.
  Walls Deck (decking)
     | 
    
   November 
  05, 2004
     | 
   
  
    | 
  Basement
  Walls Deck (armature 
  istallation)
     | 
    
   November 
  14, 2004
     | 
   
  
    | 
  Basement 
  Walls ready to be poured
   
     | 
    
   November 
  19, 2004
     | 
   
  
    | 
  Basement
  Walls poured and ready
     | 
    
   November 
  27, 2004
     | 
   
  
    | 
  Basement
  framing 90% is done 
  
     | 
    
   December 
  19, 2004
     | 
   
  
    | 
  1st floor
  framing 80% is done
     | 
    
   December 
  25, 2004
     | 
   
  
    | 
  2nd floor
  framing 75% is done
     | 
    
   December 
  31, 2004
     | 
   
  
    | 
  2nd floor
  framing 85% is done
     | 
    
  
  January 
  07, 2005
     | 
   
  
    | 
Framing done,
  Roof covered by 
  felt | 
    
February 05, 2005 | 
   
  
    | 
Sheetrock delivered, etc | 
    
February 20, 2005 | 
   
  
    | 
  
  Roof tile delivered, etc
     | 
    
March 12, 2005 | 
   
  
    | 
Ready for both stucco and 
sheet rocking | 
    
March 18, 2005 | 
   
  
    | 
Insulation done | 
    
March 26, 2005 | 
   
  
    | 
Stucco. 2nd (Brown) coat 65 % done | 
    
April 25, 2005 | 
   
  
    | 
  
  House in progress
     | 
    
  June 23, 2005
     | 
   
  
    | 
  
  House inside
     | 
    
  August 24, 2005
     | 
   
  
    | 
Landscape, driveway and 
facades are finished | 
    
September 10, 2005 | 
   
  
    | 
  
  Finishing works
     | 
    
  October 05, 2005
     | 
   
  
    | 
  
  Flyer-photos
     | 
    
  October 05, 2005 | 
   
  
    | 
  
  Existing House 
  Market
     | 
    
  December 03, 2003
     | 
   
  
    | 
	
	Property Tax 
	facts
     | 
    
  2006
     | 
   
   
  
  
 |