  February 20, 2005
  Electric done 80%
  Plumbing  
  done 85%
  Heat and sheet 
  metal done 75%
  Framing done 95%
  Concrete - 95%
  Sheetrock 
  delivered - 100%
  Roof done felted 
  100%, roof tile 0%
  Fence done 85%
 |