New house construction
Job address - 300 Sequoia Avenue, Palo alto, CA 94306-1045
Basement - 1,259 sq. ft
1st floor - 1,213.5 sq. ft
2nd - floor - 999 sq. ft
1 car detached garage (not shown) - 184.3 sq. ft

 

 

 

 

 

 

 

 

 

 

 

 

 

Old "charming house" was bought
 March 10, 2000
Surveyor Map: topo and boundary - done
 April 18, 2000
Soil Investigation service. Soil Report done
 December 31, 2000
Architect starts
 April 08, 2004
Bother. Engineer Preparation Stage
 August 01, 2004
Building Permit ready. Taxes, fees, etc. paid
 September 22, 2004
We start. Demolition
 September 27, 2004
Surveying and Holes drilling for Stitch peers
 September 29, 2004
Basement. Digging the trench for basement
 October 04, 2004
Basement. Forms installation start
 October 07, 2004
Basement. Gravel and plumbing done
 October 13, 2004
Basement. Floor waterproofing done
 October 18, 2004
Basement. Floor armature done
 October 25, 2004
Basement. Cement was poured, concrete floor done
 October 29, 2004
Basement. Walls Deck (decking)
 November 05, 2004
Basement Walls Deck (armature istallation)
 November 14, 2004
Basement Walls ready to be poured
 November 19, 2004
Basement Walls poured and ready
 November 27, 2004
Basement framing 90% is done
 December 19, 2004
1st floor framing 80% is done
 December 25, 2004
2nd floor framing 75% is done
 December 31, 2004
2nd floor framing 85% is done
January 07, 2005
Framing done, Roof covered by felt February 05, 2005
Sheetrock delivered, etc February 20, 2005
Roof tile delivered, etc
March 12, 2005
Ready for both stucco and sheet rocking March 18, 2005
Insulation done March 26, 2005
Stucco. 2nd (Brown) coat 65 % done April 25, 2005
House in progress
June 23, 2005
House inside
August 24, 2005
Landscape, driveway and facades are finished September 10, 2005
Finishing works
October 05, 2005
Flyer-photos
October 05, 2005
Existing House Market
December 03, 2003
Property Tax facts
2006