New house
construction
Job address -
300 Sequoia Avenue, Palo alto, CA 94306-1045
Basement - 1,259
sq. ft
1st floor -
1,213.5 sq. ft
2nd
- floor - 999
sq. ft
1 car detached
garage (not shown) - 184.3 sq. ft
Old "charming
house" was bought
|
March 10, 2000
|
Surveyor Map: topo and boundary - done
|
April 18, 2000
|
Soil
Investigation service. Soil Report done
|
December 31, 2000
|
Architect starts
|
April 08, 2004
|
Bother. Engineer
Preparation Stage
|
August 01,
2004
|
Building Permit
ready. Taxes, fees, etc. paid
|
September
22, 2004
|
We start.
Demolition
|
September 27, 2004
|
Surveying and
Holes drilling for Stitch peers
|
September
29, 2004
|
Basement.
Digging the trench for
basement
|
October 04, 2004
|
Basement. Forms
installation start
|
October 07, 2004
|
Basement. Gravel and plumbing done
|
October 13, 2004
|
Basement. Floor
waterproofing done
|
October 18, 2004
|
Basement. Floor armature
done
|
October 25,
2004
|
Basement.
Cement was poured,
concrete floor done
|
October 29, 2004
|
Basement.
Walls Deck (decking)
|
November
05, 2004
|
Basement
Walls Deck (armature
istallation)
|
November
14, 2004
|
Basement
Walls ready to be poured
|
November
19, 2004
|
Basement
Walls poured and ready
|
November
27, 2004
|
Basement
framing 90% is done
|
December
19, 2004
|
1st floor
framing 80% is done
|
December
25, 2004
|
2nd floor
framing 75% is done
|
December
31, 2004
|
2nd floor
framing 85% is done
|
January
07, 2005
|
Framing done,
Roof covered by
felt |
February 05, 2005 |
Sheetrock delivered, etc |
February 20, 2005 |
Roof tile delivered, etc
|
March 12, 2005 |
Ready for both stucco and
sheet rocking |
March 18, 2005 |
Insulation done |
March 26, 2005 |
Stucco. 2nd (Brown) coat 65 % done |
April 25, 2005 |
House in progress
|
June 23, 2005
|
House inside
|
August 24, 2005
|
Landscape, driveway and
facades are finished |
September 10, 2005 |
Finishing works
|
October 05, 2005
|
Flyer-photos
|
October 05, 2005 |
Existing House
Market
|
December 03, 2003
|
Property Tax
facts
|
2006
|
|