City of Cupertino, Department of Public Works Check List:
Approvals
RALPH A. QUALLS, JR. RCE 22046 09/30/05
DATE IV (A) Sheet number and number of sheets in project (B) Border line (C) Trim Line V. Key Map, showing relationship of subdivision to surrounding important streets, (North Arrow) - minimum scale 1' = 1000' VI. Improvement Plan Master Sheet (map of entire subdivision at a scale 1" = 100', 60', 50', 40'). Indicate sheet number (one of four, etc.) for each street(A) Cross gutters, sewerage system, storm drain system (B) Lot lines and numbers (C) Electroliers - designate by letter symbol and indicate light pattern (Conduit to be shown on this sheet only) (1) Correct symbols (D) Water system (1) Mains (size and distance from property line and sanitary sewer) (2) Valves (3) Fire HydrantsVII. (A) The following type of table shall be shown for street sections:
VIII. Utility Trench Section shell be in accordance with City Standard Detail 4-24, or show a Trench Detail for utilities ----------------- |