Daniel Fulga
Frame, Labor

“APPROVED”

 

Fatekh Vergasov

Owner-Builder

470 Ruthven Ave.,

Palo Alto, CA 94301-1222

 


From: dan fulga [mailto:dnj.fulga@verizon.net]
Sent: Friday, March 25, 2011 11:35 AM
To: 'Fatekh Vergasov'
Subject: FW: FulgaFRAMINGBid_1.doc

 

Fatekh,

 

Please reply back with “APPROVED” for each of the individual trades bids that I provided already – acknowledging that you are now in contract for the respective trade, and it’s your final decision.

 

Thanks,

Dan

 

Framing $35,000.00 Total (exterior windows and exterior doors installation, including front entry door install)

Complete rough framing labor only: snapping out, plating, detailing, joist, sheath, wall framing, plum and line, shear, all hardware installation (straps, holddowns, A35, etc.) set beams, cut and stack roof, eve soffits, sheathing, stair case, nailing of shear and roof sheathing to complete rough framing per HD design plans dated 12/28/10 plan check rev 2.

Note: main house 2617sf (1611sf 1st + 1006sf 2nd flr) and detached garage/porch 420sf (20ftx21ft) for a total of 3,037sf

Note 1: All materials including lumber paid and delivered to site by owner, and contractor takes responsibility for materials once delivered to the site. 

Note 2: Lumber and hardware takeoff provided by framing contractor

Note 3: Windows, sliding doors and main entrance door will be installed by framing contractor, and once delivered to the site the responsibility is transferred to the framing contractor for the materials;

Inside doors – not included, installed by other finishing-framer;

Installation included of decorative corbels ordered as precut wood by owner;

Installation included of eaves 1x6 v-rustic pine on top of the rafters

Note 4: Any Test is to be provided by Contractor, who made the job or service. But payment for test(s) will be made by Owner; Owner will pay for those job, service, material which are straightly assigned to him; Contractor will pay material, job, service, which was missed in the Bid or Quote

               Note 5: All debris generated from framing construction activities is the responsibility of the contractor

 

Payments for both House and Garage shall be as follows:

               1st Payment  $5,250.00

Snapping out, plating, subfloor

15 % of labor                                         

2nd Payment  $5,250.00

First floor framing walls, sheer panel and joisting.

15 % labor  

3rd Payment  $5,250.00

Second floor framing walls

15% labor                                          

4th Payment  $5,250.00

sheer panel and roof

15 % labor     

5th Payment  $5,250.00

Stairs and ceilings

15 % labor    

Final frame inspection passed Payment  $8,750.00  – balance will be paid 

25 % labor     

+++++++++++++++++++++

Total – 100% of the sum of $35,000.00

 

Dan Fulga

21900 Old Santa Cruz Hwy

Los Gatos, CA 95033

Lic#938344


index

 